Built for Big Spring's ground
The Loutre River hills drop off the claypan upland that covers much of Montgomery County. Claypan drains slowly and carries a perched water table in winter and spring, while hill ground moves water fast and cuts shoulders. Both fail pavement without drainage work. We ditch, grade and compact before placing asphalt.
Bids are only comparable when they spell out the same things: base depth, compacted thickness, how edges are finished, and where water is meant to go. Ask for those before you pick a number.
Compacted asphaltTypically 2 to 3 in. for a car drive
Stone baseTypically 4 to 8 in., compacted
Drive on itUsually 2 to 3 days, longer in heat
First sealcoatTypically 6 to 12 months after paving
Typical ranges. Your Big Spring estimate is sized to the soil, the traffic and the drainage on your property.